Wednesday 29 April 2015


Central London building collapse
Hundreds of people were cleared from an area of Central London and at least one person was injured after a building collapsed at a construction site last week.
Emergency services were called to Serle Street and Portugal Street in Holborn after witnesses reported hearing a "massive crash" and seeing plumes of dust.  The 6-storey building has been under demolition and part of the buildings structure, as well as the scaffolding around it, had collapsed.
A 56-year-old man was treated at the scene before being taken to hospital with serious head and hip injuries after the incident on 20 April 2015.
Around 200 people were cleared from the area and an air ambulance was seen arriving at nearby Lincoln's Inn Fields.
A spokesperson for London Fire Brigade, said: "When the first crews arrived they found the building, which was under refurbishment, had collapsed between the fifth and second floors.  Firefighters gave first aid to an injured man on site until ambulance crews arrived and also helped police put safety cordons in place and to evacuate people from the immediate area."

Construction client in court after concerns raised over work at height
Mark Hewitt, a construction client from Birmingham, was fined £3,000 and ordered to pay £1,255 in costs for failing to properly plan or manage construction work.
HSE inspected the site after a member of the public raised concerns over work taking place next to a public pavement. During the inspection it was clear there was a risk of materials falling from the first floor level onto the pavement and the street, and there were no fall prevention measures in place to protect workers on the site.
HSE Inspector Chris Gregory said:
“As the client for the work, Mr Hewitt should have ensured the appropriate measures were in place in order to plan, manage and monitor the project. He was informed of his duties by his advisors, but failed to act.    
Mr Hewitt had a duty to ensure that the safety of those working on site and those members of the public, passing by, were not put at risk, he failed on both counts”
Mark Hewitt of Manor Lane in Halesowen, being a client as defined by the Construction (Management and Design) Regulations 2007, was found guilty of breaching Regulation 9(1) of said regulations.

Firm firmed after worker’s roof fall causes ‘life-threatening’ injuries
Lockheed Martin UK Ampthill Limited was fined £10,000 (and ordered to pay more than £7,300 in costs) after admitting a breach of Work at Height Regulations.
Appearing at Luton Magistrates’ Court, the manufacturing company pleaded guilty in relation to its role in an incident in January 2012, when a contractor fell from a roof.
The man was working on the roof at its site in Ampthill, Bedfordshire where he fell through a skylight and suffered injuries that needed emergency life-saving treatment.
The company must also pay a £120 victim surcharge.

Builders sentenced over scaffold fall
A building firm was fined £11,000 with costs of £7,729 after a site manager dismantled scaffolding and later fell from it.
At Westminster Magistrates’ Court heard Abridge Developments Limited of Epping Upland, Essex, failed to plan, manage and monitor the construction work.
The company was found guilty of breaching Construction Design and Management Regulations (CDM) 2007 Regulation 22.

Fatality at construction site leads to fine
Mark Hammond was fined £12,500 after a 21 year old worker was electrocuted whilst carrying out works in the communication room in a basement on a construction site.
Hammond, of Church Gresley, Swandicote, Derbyshire, the director of Hamtech (UK) Electrical Services Limited, pleaded guilty at Southwark Crown Court to breaching Section 3 (1) of Health and Safety at Work etc. Act 1974. The defence was ordered to pay the prosecution costs of almost £50,000.
This prosecution arose out of an investigation into a fatal incident at the construction site at Great Peter Street, London on 6 July 2011.
 
CDM changes made simpler... Key changes of the new CDM Regulations 2015
Construction sites are one of the most hazardous working environments in the UK. Workers are exposed to many dangers on a daily basis that could result in injury or even death. The CDM (Construction (Design and Management) Regulations 2015 aim to reduce the risks on constructions sites and make them safer for everyone by assigning roles and responsibilities to all involved.
1. All projects must have:
- Workers with the right skills, knowledge, training and experience
- Contractors providing appropriate supervision, instruction and information
- A written construction phase plan
 2. Project where more than one contractor is involved (domestic or non-domestic) must have 1 above plus:
 
- Principal designer and principal contractor must be appointed
 
- A health and safety file
 3. If work is scheduled to:
- last longer than 30 working days and 
- have more than 20 workers working simultaneously at any point in the project
- OR exceeds 500 person days then…
All of 1 and 2 above plus:
- Client must notify project to HSE 
CDM 2015 began 6th April 2015. For projects that started before then, transitional arrangements apply.
When do the construction CDM regulations apply? The CDM Regulations apply to all construction projects where people are at work.
 
What is the definition of ‘construction work’? ‘Construction work’ is extensive and includes most building, civil engineering or engineering construction work including demolition, new-builds, refurbishments etc.
What are ‘notifiable’ projects?
A project is notifiable to HSE (the Health and Safety Executive or Inspector) if:
  • the construction phase lasts longer than 30 working days AND will have more than 20 workers working SIMULTANEOULSY at any point in the project; OR
  • if the project exceeds 500 person days. Notification is via the F10 Form.
Clients are organisations or individuals for whom a construction project is carried out and they must make suitable arrangements for managing a project.
Domestic clients are people who have construction work carried out on their own home, or home of a family member not done as part of a business. Their duties are normally transferred to the contractor, on a single contractor project; or the principal contractor on larger projects.
Designers are those who prepare or modify designs for a building, product or system relating to construction work. They must try to eliminate, reduce or control foreseeable risks that may arise.
Principal designers are designers appointed by the client in projects involving more than one contractor. They must plan, manage, monitor and coordinate health and safety in the pre-construction phase and prepare and provide relevant information to other duty-holders.
Principal contractors are contractors appointed by the client to coordinate the construction phase of a project where it involves more than one contractor. They must plan, manage, monitor and coordinate health and safety in the construction phase of a project.
Contractors are those who do the actual construction work and can be either an individual or a company. They must plan, manage, coordinate and monitor work under their control so it is safe.
Workers are the people who work for or under the control of contractors on sites. They must:
  • be consulted about matters which affect their health, safety and welfare;
  • take care of their own health and safety and others who may be affected by their actions;
  • report anything they see which may endanger either their own or others’ health and safety;
  • co-operate with the employer, fellow workers, contractors and other duty-holders.
 

 

No comments:

Post a Comment